Exiting a colocation facility or data center lease
Colocation contracts and data center leases end on fixed dates, and facilities expect the space returned empty and clean. A decommission done in a rush leaves money on the table, since enterprise hardware loses resale value every month, and risks fees for overstaying. Start planning as soon as the end date is set.
Timeline
- 6 months out. Confirm the contract end date, notice requirements and the facility's move-out conditions. Start the migration plan for workloads.
- 4 to 5 months out. Get decommissioning quotes with labor and resale credits as separate lines. Check each provider's experience in your facility.
- 2 to 3 months out. Lock the de-install schedule with the facility: escort rules, badging, dock windows and after-hours access.
- Cutover. Production moves first. De-installation follows in an agreed order, with each device matched to inventory before it's unplugged.
- Final weeks. Remove racks, cabling and power gear if the contract requires it, and walk the space with the facility.
- Close-out. Reconcile the asset report, collect destruction certificates and resale proceeds, and close the contract.
What usually needs retiring
- Servers, storage arrays and SAN switches
- Network and security appliances
- Racks, cable management, PDUs and cabling, if the contract requires removal
- Tape libraries and backup media
Where things go wrong
- Missing the end date and paying holdover fees
- Equipment shipped back to an office and forgotten instead of sold while it has value
- Network devices resold with configurations that reveal credentials or network layouts
- No reconciliation, so a missing server goes unnoticed
Services that fit
- Data center decommissioning
Planned removal of servers, storage, networking, racks and power equipment from a data center, colocation cage or server room, with data destruction and asset recovery. - Server and network equipment recycling
Removing and recycling servers, storage arrays, switches, routers, firewalls and UPS equipment, with data destruction and resale of components that still have value. - IT equipment buyback
Selling used laptops, phones, tablets, servers and networking gear to a provider who wipes the data, pays you for what has resale value and recycles the rest.
Planning by state? Start from our state-by-state e-waste law table, or build a bid request with the RFP builder.
Common questions
How long does a colocation decommission take?
A few racks can be cleared in a day or two once workloads are migrated. Larger cages take weeks. Most of the time goes into planning, migration and facility scheduling, not the physical work.
Who removes the racks and cabling?
It depends on the contract. Some facilities own the racks; others require the space returned bare. Check your contract and include removal in the decommissioning quote if needed.
Sources